SNIP 3.01.04-87 - The acceptance of the completed construction projects.fundamentals

click fraud protection

SNIP 3.01.04-87 - The acceptance of the completed construction projects.The main provisions of

building regulations

commissioning of completed construction

OBJECTS

SIGNIFICANT

SNIP 3.01.04-87

designed control standards and technical regulations in the construction involving TSNIIOMTP USSR State Committee, the Consolidated Department of capital investmentsGosplan, the Technical Administration of the USSR construction, Planning and economic Department of the State Bank of the USSR, the statistics of the Office of capital construction CSB and the Department of labor protection of the All.

prepared for approval by the Office of standardization and technical standards in the construction of the State Construction Committee of the USSR (AI Golyshev, Chuev VI).

With the introduction of SNIP SNIP 3.01.04-87 loses force III-3-81 «acceptance of the completed construction projects.The main provisions. "

When using the standard document should take into account the changes approved building codes and state standards, published in the journal "Bulletin of construction machinery", "Compendium of changes to building regulations," State Construction Committee of the USSR and the information signs "State Standards of the USSR" State Standard of the USSR.

State Construction Committee of the USSR (the USSR State Committee for Construction)

Building Regulations

SNIP 3.01.04-87

acceptance of the completed construction projects.The main provisions of

Instead SNIP III-3-81

1. GENERAL PROVISIONS

1.1.These rules and regulations shall govern the acceptance of the completed construction (reconstruction, extension), objects (enterprises, their separate queues starting complexes, buildings and structures).

1.2.On receipt of facilities must comply with current legislation and the acceptance rules in the operation of completed construction projects with the specific conditions of production for the respective branches of the national economy and industry, approved by the ministries and departments of the USSR by agreement with the State Construction Committee of the USSR, the relevant trade union central committees and interested public oversight bodies.

acceptance into operation of production facilities after the technical upgrade is carried out taking into account the requirements of the Council of Ministers Decree of January 23, 1981 № 105 in the manner prescribed by the ministries and departments in consultation with the Central Committee of the trade union and the interested public supervisory authorities.

Completed the construction of the USSR State Agricultural Committee system of objects taken into operation in the manner prescribed by these rules and the USSR Council of Ministers Resolution of 20 March 1986 № 358.

Completed construction of individual houses with farm buildings taken into service state acceptance commission in orderestablished by the Council of Ministers of the Union republics.

1.3.Predpriyatie, shop, station, production can be adopted and put into service only if they provide the working conditions in accordance with the requirements of safety and sanitation.

Approved by Decree of the State Construction Committee of the USSR
on April 21, 1987 № 84

term administration

into effect January 1, 1988

1.4.Trained to operate facilities completed construction in accordance with the approved project for the customer (the developer) shall present to the acceptance of the state acceptance commission.

Objects completed the construction, handed over "turnkey", the contractor together with the customer shall present to the acceptance of the state acceptance commission.These objects should be taken into operation in the manner prescribed by these rules.

1.5.Prior to the presentation of objects state acceptance committee working committee appointed by the customer (the developer) must check: matching objects and mounted equipment projects, compliance of construction and installation work requirements of building regulations, test results and comprehensive testing equipment, prepared facilities for the exploitation and production ofproducts (services), including the implementation of measures to ensure them the working conditions in accordance with the requirements of safety and industrial hygiene, protection of the environment, and only after that take objects.

result of comprehensive testing of equipment on operating modes of production facilities should be the beginning of output (services) envisaged by the project, in the amount corresponding to the standards development project capacities in the initial period.

1.6.Detached buildings and facilities, built-in or attached premises of production and auxiliary facilities, buildings (rooms) of civil defense, are part of the object, if necessary, putting them into effect in the course of construction of the facility taken into operation by working commissions as they become available, followed by the presentation of theirState acceptance Commission, the host entity as a whole.

Working Commission accepted into service as the titular temporary buildings and structures, construction of which is carried out with funds provided by the head of the "temporary buildings" consolidated budget calculation of construction cost.

1.7.Completed the construction of manufacturing facilities are subject to acceptance into operation the state acceptance commission only when they are ready for use (equipped with operational staff, provided energy resources, raw materials, etc.), They eliminated deficiencies on installed machinery started manufacturing products (services) provided for the project, in the amount corresponding to the standards development project capacities in the initial period.

Experienced (pilot), pilot-scale factories, workshops and installations are subject to acceptance into operation in the case where they are prepared to conduct experiments or production of the product envisaged by the project.

not allowed to acceptance into operation of production facilities, which, in violation of the established order of changes in the composition of the starting complexes envisaged by the project.

In exceptional cases, changes in the composition of the starting complexes can make authority that approved the project (for projects approved by the Council of Ministers of the USSR, after a preliminary review of the changes of the USSR State Planning Committee and the USSR State) until the appointment of the State Acceptance Commission.At the same time from the start-up facilities should not be ruled out buildings and facilities: sanitary and domestic, to ensure working conditions in accordance with the requirements of safety and industrial hygiene techniques, effective cleaning, decontamination, capture harmful emissions into the atmosphere, water and soil;recycling of waste products;driveways;communication lines and reclamation activities.

Changes to the composition of the starting complexes associated with the specification of the input of production capacities in the plan for economic and social development of the USSR, with the permission of the Council of Ministers of the USSR.

Annual acceptance into operation of irrigated and drained lands may be in the process of construction of irrigation and drainage systems after the implementation of the construction of irrigation and drainage network, water management facilities, the facilities necessary for the normal operation of systems, land use and other works included in the starting complex.On irrigation and drainage systems to the duration of the construction is not more than one year, and if necessary operation of land in agricultural production is allowed one acceptance of the land to the completion of construction in accordance with the project.

commissioning of commercial fish farming facilities should be completed before November 1 of the respective year.

commissioning of the last launch complex should be carried out simultaneously with the acceptance of the object as a whole or the last line.

1.8.Completed the construction of housing and civil purposes are subject to acceptance into operation the state acceptance commission only after all construction and installation works, landscaping, security facilities equipment and supplies in full accordance with the approved projects, as well as after the removal of defects.

Dwelling houses and public buildings of a new residential district are subject to acceptance for use mainly in the form of a complete urban complex, which should be completed by the construction of institutions and companies related to the public service, all the work on engineering equipment, landscaping and gardening territory in accordance withapproved the project of building the neighborhood.

When planned commissioning of facilities in the I and IV quarters and for the northern zone of the RSFSR, and in the month of April, and compliance with the normative terms of construction allowed the postponement of the implementation of certain types of works in accordance with mandatory applications 6 and 7.

1.9.Multi-section homes, consisting of four sections and more, can be taken into operation in separate sections, where provided by the project, the plan of capital construction and the title list with the full completion of constructions installation and heating connection to adjacent sections, as well as the completion of landscaping adjacentdonated to the section, taking into account the requirements of para. 1.8.

Completed construction of residential buildings, as well as the section of the multi-apartment houses with built-in, built-in and attached, attached premises for companies and trade establishments, public catering, consumer services and the needs of the non-industrial nature, should be taken into operation simultaneously with the above premises.

If built, Built-attached, attached premises belong to several residential sections, section by section acceptance should be made subject to completion of all construction works and provide heat at the premises of this section.Acceptance into operation built-in, built-in and attached premises in this case is carried out simultaneously with the acceptance of the last section.

commissioning of enterprises and institutions located in the built-in, built-in and attached, adjoined rooms, should be implemented by a separate act of the respective state acceptance commission.

1.10.Sewage treatment facilities newly built, extended or reconstructed objects shall be subject to acceptance into operation after hydraulic testing of pipelines and capacitive structures, long (not less than three days), comprehensive testing under load on a clean or waste water, and after checking the interaction in all the facilities.

Note.Adjustment process of biological sewage treatment must be carried out after acceptance of treatment facilities in operation at zero temperature of air at night and not less than 10 ° C during the day no later than the following dates:

capacity of treatment facilities, thousand cubic meters / day..

limit the duration of the setup, months.

Up 0.7 incl.

3

St. 0.7 to 10 "

5

" 10 "40"

8

"40" 130"

9

" 130 "175"

10

"175" 280 "

11

" 280 "350"

12

"350

13

1.11. The date of entry into operation shall be the date of signing of the State acceptance Commission.

date of commissioning of the facility, received according to para. 1.6, is the date of signing of the act of the working committee.

2. RESPONSIBILITY OF THE PARTIES

2.1.Customers (developers) are responsible for the timely preparation for the exploitation and production of products (services) put into effect the objects (staffing of personnel, provision of raw materials, energy, etc..), For carrying out comprehensive testing (off-load and operating conditions) equipment withdesign, construction and installation organizations, and if necessary - and plants - manufacturers of equipment for the setting up of processes, commissioning of production capacities and facilities in a timely manner, output (services) and development of design capacity within the timeframe stipulated by the regulations in force.

2.2.Design organizations are responsible for matching capacity and other technical and economic parameters of objects put into operation, capacity, and performance provided by the project, and for the resolution of issues associated with the design, resulting in the acceptance of objects in operation and development of their design capacity.

2.3.Research organizations are responsible for ensuring they have issued the original data for the design of scientific and technological progress in the field of new technological processes, equipment and materials.

2.4.Construction organizations are responsible for the execution of construction and installation work under the project and in a timely manner, for the quality of these works, conducting individual testing equipment mounted to, the timely elimination of deficiencies identified in the course of acceptance of construction and installation works and comprehensive testing equipment, the timely commissioning of production capacities and facilities.

2.5.In case of violation of the rules of acceptance of the completed construction of facilities chairpersons and committee members, as well as persons to compel acceptance of the facility in violation of these regulations, subject to administrative, disciplinary and other liability in accordance with applicable law.

3. Working Commission, THEIR RIGHTS, DUTIES AND OPERATION

3.1.Working Committee appointed by the decision (order, decree, etc.) Of the contracting authority (the developer).The order and duration of the working commissions determined by the customer (the developer) in agreement with the general contractor.

3.2.The working committees include representatives of the customer (the developer) - Chairman of the Commission, the general contractor, subcontractors, operating the organization, the general designer, public health surveillance bodies, the state fire supervision.State Inspectorate for Air Protection at the USSR State Committee for Hydrometeorology and Monitoring of the natural environment1, Technical Labour Inspection of the Central Committee or the relevant council of trade unions, trade union organization or the customer's operational organization.At the commissioning of housing and civil purposes in the working commissions included architects - authors of projects (deputy chairman).

(Revised edition. Chg. Number 1).

___________

1 for production facilities.

When commissioning of buildings, structures and premises referred to in para. 1.6, to participate in the working committees in addition involved representatives of concerned organizations and supervisors.

3.3.Working committees are established no later than five days after receiving written notice of the general contractor on the readiness of the facility or the equipment to pass.