Oven barbecue made ​​of bricks with their hands

click fraud protection

Oven BBQ at the cottage - an indispensable structure, which allows fast and comfortable to cook a variety of delicious dishes for friendly get-togethers.This oven barbecue can be folded out of bricks with their hands.This furnace is universal, safe and this area is the decoration.

Oven barbecue made ​​of bricks with their hands

barbecue oven made of brick with his hands

Run barbecue oven made of brick with his own hands is not too difficult, it is important to stock the necessary materials and follow the technology closely.

Stages of work

to build a reliable and beautiful barbecue oven made of brick with his hands, you must strictly follow the technology at every stage of the work.It is particularly important to comply with all the recommendations, if your experience in masonry small - it will help to avoid further alterations.

  1. Performing drawing and specification of the required amount of materials.By drawing determine the exact dimensions of all components, and the amount of waste can be significantly reduced.
  2. Performing formwork and pouring of the foundation.The foundation for a barbecue oven must be strong enough to withstand its weight.The expediency of deepening of the foundation below the freezing depth, especially on silnopuchinistyh grounds, questionable - just run slab reinforced foundation a minimum thickness of 30 cm on the heaving and moist soil foundation laid on the sand-gravel cushion with waterproofing -. This will help to avoid strain stove and its foundation in the cold.
  3. masonry oven.It is performed after complete solidification of the foundation, i.e. 3-4 weeks after casting.Lay bricks on the cement-sand mortar of medium thickness with jointing - so the stove will look much more elegant without lining.It is not necessary to use a heat-resistant bricks for the entire furnace can be put out of it only brazier wall.

Set pan angle, grill, table tops and shelves.Finishing the floor under the stove tiles and laying of roofing iron pipe.

Performing drawing and calculation of materials

drawing furnace brick barbecue shown in the figure.Offered oven is made on the basis of concrete, has two compartments - a brazier and a work cutting table.In the table, if desired, can be embedded sink.Brazier ends arch and pipe, which helps to avoid the smoke generated by traction.

drawing furnace

drawing furnace

Follow-laying technology is designed precisely for such an oven, but you can make adjustments to the drawing and more resize it if desired.. It is necessary to start from the standard size bricks 25h12h6 see

to that shown in Figure stove will need:

  • Brick - about 350 pieces;
  • Cement and Sand for solution;
  • M200 Concrete pouring of the foundation - about 0.7 cube;
  • reinforcement for the foundation: grooved rod D12 - about 25 meters;
  • Corner 45 mm - two segments by 1030 mm;
  • iron sheet to perform tray for coal with a thickness of 4 mm;
  • Grill grates;
  • Table top of MDF;
  • waterproof plywood shelves to perform;
  • Porcelain tiles or floor tiles for finishing the basement;
  • adhesive tiles or granite;

sheeting or roofing iron pipe.

Pouring the foundation

Foundation for the furnace

foundation under the stove

  1. By pouring the foundation necessary to begin only after the preparation of the site.First remove the fertile layer of soil and mark out the dimensions of the foundation - for the convenience they need to be on each side by 10 cm longer than the dimensions of the stove.If the stove will be arranged around the gazebo with a wood floor, the front side in order to better carry out fire safety pad width of about 60 cm.
  2. The layout is performed by Roulette and polygon.In the corners of the foundation of the future of hammered pegs and pull the string between them.To check the layout and check the squareness of angles equal diagonals.By marking fulfill the trench depth of 0.3 meters.
  3. for devices waterproofing cushions bottom of the trench is filled gravel layer, then a layer of coarse sand.The thickness of each layer -. 10-15 cm pillow layers shed water and thoroughly compacted.
  4. Perform formwork above the soil level of the planed boards, fastened with self-tapping screws.Formwork height - 10 cm above the ground.On loose soils formwork must be done throughout the entire depth of the trench.
  5. Perform armirovanie.Prutok D12 cut to equal length and width of the formwork and placed in a grid with 20 cm increments. In places of crossing bars associated soft wire with a hook for the accessories.You must perform two series of valves, one lay on the bottom of the formwork, the second raise to the level of 5 cm below the top.
  6. procuring ready-mixed concrete grade M200 or prepare their own concrete in accordance with the calculation.Pour the foundation concrete and punch using vibrator.Align the surface of the concrete rule.

Concrete Curing lasts several weeks.Care should be taken that there is no drying out of its upper layer, for which the foundation is covered with foil.The formwork can be removed after a week.

furnace masonry

  1. To begin laying the concrete after curing and formwork removal.Prior to the laying of the foundation is marked on the furnace dimensions.Laying begin by marking in accordance with the scheme by checking the horizontal level in all directions.For masonry using cement-sand mortar, mixed in a ratio of 1: 3 or 1: 4.
  2. first four rows are placed stretcher ligation in accordance with the scheme, after application of the fourth row in front of the oven is placed corner 45x45 mm - it will serve as a support for the fifth series.The fifth row is placed on the side walls ligation binder so as to form supports for shelves and pallets.

    Laying of the first furnace series

    Laying the first furnace series

  3. sixth, seventh and eighth series again put the stretcher ligation, and the ninth row is performed similarly to the fifth perevyyazkoy binder to form a support for grating and countertops.

    6,7,8 series put stretcher ligation

    6,7,8 ranks put stretcher ligation

  4. Building on this table is completed, and further laying is done only from the barbecue oven.Rows from 10 th to 14 th put the stretcher again ligation scheme, after laying 14 goryada from the front lay area 45x45 mm, which will serve as a pillar of the furnace roof.Perform the 15th row.

    Laying 10-15 series

    Placement 10-15 series

  5. Then begins laying the furnace roof, which gradually narrows.Perform this restriction due to alternating stretcher and bonder series and the displacement of masonry to the center.16th row binder ligation placed on the front side, and the 17th - both sides, 18th - again from the front, but with an offset number.This forms three projections, which can be used as a shelf.

    Masonry oven 16 to 18, a number of

    Laying oven 16 to 18, a number of

  6. 19th number put stretcher masonry, forming another regiment.20 th and 21 th ranks put stretcher ligation scheme.

    From 19 to 21 put the number of locust bean masonry

    from 19 to 21, a number of lay laying locust bean

  7. Since the 22th row is performed laying pipe.The restriction in the pipe 23 th row forms another shelf and then clutch continues until the desired height without restriction.It should be remembered that the height of the pipe directly affects traction, and the higher it is, the better the removal of smoke.

    Sample pipe laying for the furnace

    sample tube furnace masonry

  8. penultimate number forms a smoke box, after which the pipe is laid on top.This furnace masonry shall be deemed terminated.Drying the solution lasts for about a week, after which you can start decorating.
    Masonry flue windows

    masonry flue windows

finishing

At this point, the oven must be installed on the pan of coals and grill, countertop and shelves.Pallet perform yl sheet metal in the form of a rectangular sheet with upturned front edge.The height of the rim -. At least 5 cm grid can be purchased ready-made, chrome, or use the right size of the grill oven.Shelves and countertops made from moisture-resistant MDF, and fix them in a batch using the furniture dowels in accordance with the drawing.

On top tube set the roof profiled roofing iron, and the length of the ramps should be such as to prevent ingress of driving rain in the smoke box.Foundation to make it water-repellent properties of the top can be finished with granite and tiles, placing them on the tile adhesive.

The oven is ready for barbecue

Oven BBQ ready

This barbecue oven made of brick, made with their own hands, can become the basis of the gazebo for relaxing in the fresh air.The functionality of the furnace can be extended and turn it into a smokehouse if weld iron smoking chamber constructed in accordance with the size of the lattice for a grill.