Putting electricity into a private house : paperwork and conditions

Specifications

first thing you need to arrange for a centralized network, is to obtain specifications for the electrification of the local power grid organization.There is likely to be sent to the intended consumer Customer Service Center (CSC).

With a need to have:

  • passport and a photocopy of your passport;
  • land documents and a copy of the certificate or at home with a copy of the plan and section.

In TsOKe need to write an application for connection to the power grid in two copies (one signed by the host country and the date, leave at).After 30 days, the application shall be considered and the contract is concluded.

Important!Refuse to contract the provision of all documentation electricity supplier can not legally!Putting electricity into a private house : paperwork and conditions

electrification Terms When a contract for electricity entering a private home be sure to read it completely, because it can slip through excessive demands on the applicant, etc.Also note that if the nearest point of the network outside the station the user is within a mile, all work on the wrapping lines to the site run energy supplier for no longer than six months.

Tighten the connection of electricity to the private house can still be through project documentation.It is important to know that it is made by the applicant and without process connection to the network is not possible.Legislative exception is construction, overhaul and reconstruction of private housing.

After receiving the specifications and the contract should be immediately begin to perform prescribed in these terms:

  • metering units are mounted on the outer wall of the housing or support;
  • mounted cable laying from the metering unit to the site boundary (better to have a reserve)
  • during construction - mounted internal network (at least minimally).Putting electricity into a private house : paperwork and conditions

Permits

How to apply and where to find documents on the electricity entering a private home after the installation is carried out?All of them are also supplier of electricity in the region.You will need to obtain such papers:

  • Act I (see) metering device;
  • act delineation of operational and balance participation;
  • certificate of conformity specifications;
  • act of inspection and admission of electrical installations;
  • contract for electricity supply.

In principle, the regions may be differences in the amount of documentation, but this basic list of relevant almost everywhere.It should be clarified with the service provider.Putting electricity into a private house : paperwork and conditions

Electrification housing

Upon receipt of all necessary documentation and all of the above works, you can begin the installation (overhaul) wiring, connect chandeliers, appliances and even the battery (if needed and desired).The costs of these works are highly individual and are determined by estimates compiled by professional electricians according to the project of electrification of private homes and land.The cost of work may vary depending on the construction of the region.

listed steps paperwork for electrification and network connections show similarities procedures for connecting the private house and grounds to a central electrical supply network.In different regions of the requirements may be harder or softer.Putting electricity into a private house : paperwork and conditions